For the first time in the last 9 years, most of the road restrictions were lifted within just 12 hours after the "Formula 1" week.
According to Idman.biz, citing the Baku City Circuit Operations Company, after the completion of the Azerbaijan Grand Prix 2025, the circuit infrastructure and the grandstands at the Azneft roundabout were completely dismantled, and the central streets were returned to traffic.
On the first night of dismantling work, from 06:00, traffic was fully restored, with the exception of the section of Neftchilar Avenue from the intersection with Rashid Behbudov Street to the intersection with Pushkin Street.
It should be noted that most of the roads closed during the race week were open to drivers for certain time intervals in order to reduce traffic jams in the city.
Idman.biz