The process of replacing the grass cover of the Tovuz City Stadium, which belongs to the "Turan Tovuz" club, will be completed in the early part of next year.
Idman.biz reports with reference to Sportinfo.az that the team will remain outside its home region for at least 5-6 months.
After the artificial turf is dismantled, drainage and irrigation systems will be installed. After that, the soil part will be placed and the natural turf will be laid.
Although the official statement given a few days ago stated that the work was planned to be completed by the end of October, the renovation process will take longer. The team will not be able to return to their home field until February.
It should be noted that the team will train in Kurdakhani during this period, and will play its official matches at the "Azersun Arena" located in Surakhani.